Contractor Bids Requested

We are currently advertising the following ODNR construction projects for competitive bidding.  The following information is provided for the purpose of acquainting prospective bidders with the amount of work involved in the project.

Notices of Commencement are available upon request by emailing: Engineering@dnr.state.oh.us

For further information including specifications please visit BidExpress where interested parties may secure additional information and submit bids if interested in the project listed below.


5 Projects Found
Project Name: Boch Hollow SNP Trail Bridge & Parking
Project Location: Boch Hollow State Nature Preserve
Project Number: DNR-170109
Project Description: This project is located in southeast central Ohio at Boch Hollow State Nature Preserve; 7100 SR 664, Logan, Ohio 43138. To reach Boch Hollow SNP from Columbus, Ohio, take I-70 east to US-33 E/Southeast to Tarklin Road. Turn east on Tarklin Road SE and continue onto Horns Mill Road (63). Horns Mill Road (63) turns into Hide A Way Hills Road (82). Continue on to SR 664 S. The site will be on your left approximately 2400 past Zwickle Road. The project includes an asphalt parking lot, concrete sidewalk and railing, a pre-cast modular block gravity retaining wall, a pedestrian bridge, gravel walk, and wood steps. The site will require grading, tree removal, and restoration. All work is to be completed under one unit price/lump sum General Contract. Completion date for all work under this project is December 9, 2019.

Click here for the full description
Total Estimated Construction Cost: $415,200.00
Bid Opening Date: 5/29/2019
Cost of Bid Package:
 
Project Name: Delaware WLA Shooting Range Improvements
Project Location: Delaware Wildlife Area
Project Number: DNR-140003
Project Description: The project is located in central Ohio at the Delaware Wildlife Area, State Route 229, Ashley, Ohio 43003. To reach Delaware Wildlife Area from Delaware, Ohio, take US Route 23 north 10 miles to State Route 229. Travel east 1.3 miles to the shooting range entrance. The project involves renovation of the existing shooting range and construction of two new buildings. Major items of work include: construction of a 6,736 sq. ft. archery training center and a 245 sq. ft. range master building; redevelopment of shooting range earthen berms; construction of shooting range covered firing lines, benches and tables; construction of new entrance road and parking areas; installation of storm sewer, sanitary sewer and water lines; construction of storm water sedimentation ponds; installation of sanitary sewage pump station and on-site sanitary sewage drip irrigation system; electrical services; and construction of three archery range area. The project also includes site restoration and fencing. All work is to be completed under one unit price/lump sum General Contract. Completion date for all work under this project is August 1, 2020.

Click here for the full description
Total Estimated Construction Cost: $8,268,000.00
Bid Opening Date: 5/30/2019
Cost of Bid Package:
 
Project Name: Punderson SP Maintenance Roof Replacement
Project Location: Punderson State Park
Project Number: DNR-190027
Project Description: This project is located in Northeast Ohio at Punderson State Park; 11755 Kinsman Road, Newbury, Ohio 44065. The project involves removal of existing roof membrane, insulation, metal coping, skylights, and metal accessories to existing deck. A contractor will then provide metal decking for the two skylight voids and evaluate existing deck for replacement. Roof will be replaced with an EPDM roofing system, R-30 insulation, metal edge trim, roof hatch, guardrails, walkway pads and drain inserts as indicated. All work is to be completed under one unit price/lump sum General Contract. Completion date for all work under this project is August 15, 2019.

Click here for the full description
Total Estimated Construction Cost: $86,000.00
Bid Opening Date: 5/28/2019
Cost of Bid Package:
 
Project Name: Deer Creek Elevated Water Tank Rehabilitation
Project Location: Deer Creek State Park
Project Number: DNR-190057
Project Description: The project is located in central Ohio at the Deer Creek State Park campground, 20635 State Park Road #20, Mt. Sterling, Ohio. To reach Deer Creek State Park from Mt. Sterling, Ohio, take OH Route 207 south 4 miles to Yankeetown Rd NE. Travel east 1.5 miles to the Deer Creek State Park entrance. Follow signage to the campgrounds, the tank is visible just beyond the camp check-in to the left.The project involves renovation of one existing 300,000 gallon spheroid water tank. Major items of work include: painting the interior wet, interior dry and exterior dry areas; structural repairs and modifications; and installation of safety climb systems. The project also includes site restoration and a temporary Water System. All work is to be completed under one unit price/lump sum General Contract. Completion date for all work under this project is December 30, 2019.

Click here for the full description
Total Estimated Construction Cost: $511,600.00
Bid Opening Date: 6/11/2019
Cost of Bid Package:
 
Project Name: Six Mile Creek Aqueduct Restoration
Project Location: Miami and Erie Canal
Project Number: DNR-180034
Project Description: OH-66 Bridge over Six Mile Creek including the Canal Aqueduct over Six Mile Creek, adjacent tow path arches and surrounding embankments. The purpose of the project is to restore the recently damaged historic aqueduct structure by replacing the failed northwest wingwall, reinforce the existing southwest wingwall, and perform associated concrete, masonry, and stone channel lining improvements. The general scope of work includes: Water Control 1. Contractor to prepare water control plan sealed by a registered Ohio Professional Engineer. 2. Furnish and Install approved water control plan to manage conveyance of Six Mile Creek and Miami and Erie Canal to accommodate aqueduct structure repairs in the dry. 3. Divert or remove water from all areas of the project where permanent work is to be performed, install or construct facilities, cofferdams, diversion pipes/channels/berms, sumps, and pumping facilities as required. 4. Designing and maintaining temporary diversion facilities and for protecting the work area from flooding. Northwest Wingwall Replacement 1. Demo existing wingwall stone foundation. 2. Furnish and install reinforced concrete drilled shaft with precast concrete panel wingwall. 3. Furnish and install stone masonry veneer to match existing historic masonry. North Abutment Wall Restoration 1. Restore failed portion of stone masonry abutment wall with reinforced concrete column 2. Furnish and install soil nail tie-back anchors and steel bearing plate in existing stone masonry abutment wall. 3. Furnish and install stone masonry veneer to match existing historic masonry. Southwest Wingwall Restoration 1. Furnish and install soil nail tie-back anchor in lower portion of existing wingwall. 2. Furnish and install stone masonry veneer over anchor to match existing historic masonry. 3. Salvage and rebuild lower portion of existing stone masonry wingwall with drainage improvements. Aqueduct Structure Repairs 1. Furnish and install concrete crack seal for canal arch, two (2) tow path arches, and two canal headwalls. 2. Furnish and install concrete repair/resurfacing of spalled canal arch and two (2) tow path arches. 3. Furnish and install tuck-point repair of existing stone masonry throughout entire aqueduct structure as directed by engineer. 4. Furnish and install missing stacked stone channel lining and fluid grout joints while maintaining geometry of low flow channel. 5. Furnish and install canal arch spillway drip edge surface protection. Site Restoration 1. Furnish and Install precast tied concrete mat on embankments with soil infill per plan. 2. Furnish and Install rock channel protection of wingwalls per plan. 3. Final grade and restore project area with erosion control blankets and native grass seed. All work is to be completed under one Lump Sum General Contract. Unit prices are to be included as requested by ODNR, under the same contract. The anticipated time from Bid Opening to Notice to Proceed is 15 days. The Contract Date of Substantial Completion for all work under this Project is December 31, 2019.

Click here for the full description
Total Estimated Construction Cost: $671,080.00
Bid Opening Date: 6/7/2019
Cost of Bid Package: