Contractor Bids Requested

We are currently advertising the following ODNR construction projects for competitive bidding.  The following information is provided for the purpose of acquainting prospective bidders with the amount of work involved in the project.

For further information including specifications please visit BidExpress where interested parties may secure additional information and submit bids if interested in the project listed below.


2 Projects Found
Project Name: Statewide Cabins
Project Location: Sherman Cabins Procurement Bid Package 1
Project Number: DNR-170048
Project Description: The Project is to be located in various state parks throughout Ohio. The Project consists of procuring materials associated with the construction of 24 park cabins, to be constructed by the Ohio Penal Industries. The Work of the Project is defined by the Contract Documents. The scope is limited to supplying and delivery of the materials as outlined in the Contract Documents. The scope does not include installation of any parts. All materials are to be delivered to 16149 OH-104, Chillicothe, Ohio 45601 as part of this contract. All work is to be completed under one General Contract. Substantial Completion date (i.e. final delivery of all materials) for all work under this project is July 5, 2017..

LEARN
Total Estimated Construction Cost: $373,382.00
Bid Opening Date: 3/28/2017
Cost of Bid Package:
 
Project Name: Cutler Dam Improvements
Project Location: Blue Rock State Park
Project Number: DNR-140017
Project Description: The project is located in Blue Rock State Park, off Cutler Lake Road in Muskingum County, approximately 15 miles southeast of Zanesville, Ohio. The Ohio Department of Natural Resources (ODNR) is improving Cutler Lake Dam, located in Blue Rock State Park, in order to bring the facility into compliance with current ODNR Dam Safety Regulations. The improvements to the dam generally include: removal of the existing concrete spillway and chute, construction of a new concrete spillway and chute, modifications to the existing outlet works, construction of an earthen embankment, select demolition, and upgrades to the immediate dam area; including placement of a pedestrian bridge, a concrete culvert crossing, asphalt pavement, a picnic shelter, and an aggregate pedestrian trail. All work is to be completed under one Lump Sum and Unit Price General Contract. Completion date for all work under this project is June 1, 2018. The foregoing is for the purpose of acquainting prospective bidders with the amount of work involved on this project, and is to be used as a guide in requesting documents for this project..

LEARN
Total Estimated Construction Cost: $4,752,000.00
Bid Opening Date: 4/18/2017
Cost of Bid Package: