Contractor Bids Requested

We are currently advertising the following ODNR construction projects for competitive bidding.  The following information is provided for the purpose of acquainting prospective bidders with the amount of work involved in the project.

For further information including specifications please visit BidExpress where interested parties may secure additional information and submit bids if interested in the project listed below.


3 Projects Found
Project Name: New Galena Boat Ramp
Project Location: Alum Creek State Park
Project Number: DNR-150011
Project Description: The project involves removal and complete replacement of a concrete vault restroom facility with a new precast concrete flush facility, installation of a sewage pump station and approximately 100 lineal feet of force main, installation of approximately 100 lineal feet of water line, connection of electrical utilities to the new precast concrete flush facility, and coordination with American Electric Power for transformer relocation, and other electrical work.

LEARN MORE

Total Estimated Construction Cost: $211,000.00
Bid Opening Date: 8/4/2016
Cost of Bid Package:
 
Project Name: ODNR Restroom Improvements
Project Location: Lake Milton State Park Causeway Launch Ramp
Project Number: DNR-150065
Project Description: This project involves removal and relocation of a vault restroom facility and replacement with a new precast concrete flush facility, demolition of the existing sanitary vault, installation of approximately 300 lineal feet of gravity sewer, installation of approximately 300 lineal feet of water line, and connection of electrical utilities to the new precast concrete flush facility. This work includes directional drilling for installation of the gravity sewer.

LEARN MORE

Total Estimated Construction Cost: $212,000.00
Bid Opening Date: 8/2/2016
Cost of Bid Package:
 
Project Name: Lake Loramie Spillway Improvements
Project Location: Lake Loramie
Project Number: DNR-140065
Project Description: The project involves construction of a new principal spillway and outlet works, construction of an earthen embankment paired with a concrete floodwall, select demolition to the existing spillway and abutment wall, demolition of a State owned structure, and improvements to the immediate spillway surroundings. The project will be constructed while maintaining normal pool within the reservoir.

LEARN MORE

Total Estimated Construction Cost: $4,335,000.00
Bid Opening Date: 8/3/2016
Cost of Bid Package: