Contractor Bids Requested

We are currently advertising the following ODNR construction projects for competitive bidding.  The following information is provided for the purpose of acquainting prospective bidders with the amount of work involved in the project.

For further information including specifications please visit BidExpress where interested parties may secure additional information and submit bids if interested in the project listed below.


3 Projects Found
Project Name: Oxbow Road Boat Ramp Improvements
Project Location: Hoover Reservoir
Project Number: DNR-140008
Project Description: The main boat ramp project is located at 8401 Oxbow Road, Westerville, Ohio 43082, about 0.5 mile east of Tussic Street Road. A detention basin will also be constructed just south of Hoover Dam on the east side of Sunbury Road as a part of this project. The project involves the construction of a one-lane concrete boat ramp with floating docks and asphalt paved parking lots for 27 car-trailer spaces and 18 car-only spaces. Major items of work include excavation and fill, underdrains, aggregate base, asphalt paving, concrete, pipe piling, floating docks, rock slope protection, detention basin, vegetation, and associated drainage and erosion control structures. All work is to be completed under one Lump Sum and Unit Price General Contract. The final completion date for all components of the work under this project is May 24, 2018. The foregoing is for the purpose of acquainting prospective bidders with the amount of work involved on this project and is to be used as a guide in requesting documents for this project.

Click here for the full description
Total Estimated Construction Cost: $1,832,415.00
Bid Opening Date: 6/6/2017
Cost of Bid Package:
 
Project Name: New Restrooms at Cedar Falls
Project Location: Hocking Hills State Park
Project Number: DNR-170053
Project Description: The project is located in Hocking Hills State Park at Cedar Falls next to the pavilion, off State Route 374, near Logan, Ohio. The project is to construct a new 10-user flush restroom next to the pavilion at the Cedar Falls area in Hocking Hills State Park. Work includes constructing an ADA-compliant restroom building with separate sides for Men and Women, each side containing five water closets, two lavatories, LED lighting, miscellaneous bathroom fixtures, and heat; connecting to a new well for water service; installing a self-contained sanitary sewer system with an access drive for maintenance; connecting to a pad-mounted transformer to provide electric service to the building; installing two ADA parking spaces with appropriate striping and signage; and drainage improvements near the pavilion. All work is to be completed under one Lump Sum General Contract. Completion date for all work under this project is December 31, 2017.

Click here for the full description
Total Estimated Construction Cost: $543,000.00
Bid Opening Date: 6/6/2017
Cost of Bid Package:
 
Project Name: Conservation Ponds No.1 & 2 Dams Decommissioning
Project Location: Jockey Hollow Wildlife Area
Project Number: DNR-160023
Project Description: The project is located in the Jockey Hollow Wildlife Area, Harrison County, Ohio. The project includes the decommissioning of two earthen dams located near the entrance to the wildlife area at 75732 Nottingham-Holloway Road in Cadiz, Ohio. The dams are located along a gravel road about half a mile east of Nottingham-Holloway Road. Coordinates for the dams are as follows: 1. Conservation Pond No. 1 Dam: 40.190295, -81.112514 2. Conservation Pond No. 2 Dam: 40.189529, -81.116766 The project consists of degrading two earthen dams in the Jockey Hollow Wildlife Area, backfilling their impoundments with excavated material, and restoration of the streams running through the ponds. The general scope of work includes: 1. Dewatering of the two ponds. 2. Mass excavation and placement of an estimated 185,000 cubic yards of material. 3. Construction of boulder jam steps through the cut in each dam. 4. Placement of channel rock and live stakes to stabilize and restore about 2,700 linear feet of natural channel through the ponds and dams. All work is to be completed under one Lump Sum and Unit Price General Contract. Completion for all work under this project shall be within 158 days of the Notice to Proceed.

Click here for the full description
Total Estimated Construction Cost: $1,589,000.00
Bid Opening Date: 6/6/2017
Cost of Bid Package: